Approach for fixing problem on very urgent basis - Testing types and levels
Q. If a problem occurs in a system 6 months after it completely goes live, what will be the approach for fixing that problem on very urgent basis?- Published on 18 Aug 15a. Do not involve testers
b. Just go for retest
c. Always go for full regression test
d. Go for retest and then use risk assessment to decide reasonable subset of regression test suit that will be executed.
ANSWER: Go for retest and then use risk assessment to decide reasonable subset of regression test suit that will be executed.