Chain Rule - Quantitative Aptitude (MCQ) questions for Q. 29425

Q.  If a tank can be build by 18 men in 28 days while working for 9 hours per day, how many hours per day do 21 men have to work for 36 days, to complete the same tank?
- Published on 12 Apr 17

a. 4
b. 5
c. 9
d. 6

ANSWER: 6
 
chain rule