Chain Rule - Quantitative Aptitude (MCQ) questions for Q. 747
Q. If a carpenter completes 3/8th of his work in 6 days, then how many more days will he require completing his remaining work?- Published on 06 Jul 15a. 10
b. 12
c. 6
d. 16
ANSWER: 10
As 3/8th of the work is completed, the work remaining is 5/8th of the total.
(3/8):6::(5/8):x
x = 6*(5/8)/(3/8)
x = 10