GARV app upgraded

Q.  What does GARV stand for?
- Published on 07 Apr 17

a. Grameen Vidyutikaram
b. Gram Vidyutikaran
c. Gaon Vidyutikaran
d. None of the above

ANSWER: Grameen Vidyutikaram
 
GARV app upgradedGrameen Vidyutikaran (GARV) App has been upgraded for monitoring the villages and households electrification in the country.

GARV-II includes monitoring of electrification of habitations as well as households. It also provides an interactive platform for feedback and would help in expediting electrification works.

Government of India has launched Deendayal Upadhyaya Gram Jyoti Yojana (DDUGJY) with total investment of Rs.43,033 crore in the country in December, 2014 with the objectives of, inter-alia,

(i) Village Electrification;
(ii) Providing access to households;
(iii) Feeder Separation;
(iv) Strengthening of sub-transmission and distribution network and
(v) Metering.

Under DDUGJY, projects of an amount of INR.42553.17 crore have been sanctioned for rural electrification works which include village electrification, access to households, feeder separation, metering and system strengthening.

Initiatives to Improve Efficiency of Coal Plants: Know More
  • The Government has taken several steps to modernize and improve the efficiency of coal based thermal power plants and to reduce the pollution level of coal based thermal power plants in the vicinity of these plants.
  • Supercritical technology has already been adopted for thermal power generation.
  • The design efficiency of Supercritical units is about 5% higher than that of typical 500 MW subcritical units and these (supercritical) units are likely to have correspondingly lower fuel consumption and CO2 emissions in ambient air.
  • A capacity addition of 39,710 MW power based on supercritical technology has already been achieved and 48,060 MW of supercritical technology is in the pipeline.
  • All Ultra Mega Power Projects (UMPPs) are required to use supercritical technology.
  • Coal based capacity addition during the 13th Plan period shall be through super-critical units.
  • Indigenous research is being pursued for development of an Advanced Ultra Supercritical Technology (A-USC) with targeted efficiency improvement of about 10% over supercritical unit.
  • Indira Gandhi Centre for Atomic Research (IGCAR), NTPC Ltd. and BHEL signed an MoU, in August 2010, for development of 800 MW A-USC indigenous demonstration plant with main steam pressure of 310 kg/cm2 and temperature of 710/ 720 deg C.
  • A capacity of about 7751.94 MW of old and inefficient unit has already been retired till date.
  • To facilitate State Utilities/IPPs to replace old inefficient coal based thermal units with supercritical units, Ministry of Coal, Government of India has formulated a policy of automatic transfer of Letter of Assurance (LOA)/Coal linkage (granted to old plants) to new (proposed) super-critical units.
  • Perform Achieve and Trade (PAT) Scheme under National Mission on Enhanced Energy Efficiency is under implementation by BEE (Bureau of Energy Efficiency). In PAT cycle–II, individual target for improving efficiency has been assigned to 154 thermal power stations.
    High efficiency Electrostatics Preceptor (ESP) are installed to capture Particulate Matters from Flue gases.
  • Low NOX burners are installed for reducing NOx emission from flue gases.
  • SO2 emission control is achieved through dispersion of flue gases through tall stacks (275 metres) to reduce the concentration of polluting gases at ground level.