India is third in the world in the number of nuclear reactors being installed, at six, while China is leading at 20, the World Nuclear Industry Status Report 2017, released this month, shows.
The number of nuclear reactor units under construction is, however, declining globally for the fourth year in a row, from 68 reactors at the end of 2013 to 53 by mid-2017, the report says.
The latest report further reveals that most nuclear reactor constructions are behind schedule, with delays resulting in increase in project costs and delay in power generation.
There are 37 reactor constructions behind schedule, of which 19 reported further delays over the past year. In India itself, five out of the six reactors under construction are behind schedule.
Eight nuclear power projects have been under construction globally for a decade or more, of which three have been so for over 30 years.
Data gathered by the authors shows that global nuclear power generation increased by 1.4% in 2016 due to a 23% increase in China, though the share of nuclear energy in electricity generation stagnated at 10.5%.
By comparison, globally, wind power output grew by 16% and solar power by 30%. Wind power increased generation by 132 TWh (terawatt hours) or 3.8 times, and solar power by 77 TWh or 2.2 times more than nuclear power’s 35 TWh respectively.
Renewables represented 62% of global power generating capacity additions.
Russia and the U.S. shut down reactors in 2016, while Sweden and South Korea both closed their oldest units in the first half of 2017, the report notes.
The report also documents the financial crisis plaguing the industry. After the discovery of massive losses over its nuclear construction projects, Toshiba filed for bankruptcy of its U.S. subsidiary Westinghouse, the largest nuclear power builder in history.
AREVA has accumulated $12.3 billion in losses over the past six years.