Modules are not required to be completed before Integration Testing starts

Q.  In Big Bang Integration, all the modules are not required to be completed before the Integration Testing starts.

- Published on 13 Aug 15

a. True
b. False

ANSWER: False
 

    Discussion

  • Prajakta Pandit   -Posted on 17 Nov 15

    - The above statement is false.

    - In big bang integration testing, all components or modules are integrated.

    - It has an advantage that the entire process gets finished before the integration testing starts.