Numerical - Calculate B.E.P capacity for given fixed cost & percentage of variable cost

Q.  Calculate B.E.P capacity if Fixed cost is Rs 50,000, percentage of variable cost is 66 2/3% and capacity is Rs 3,00,000.
- Published on 15 Sep 15

a. 25%
b. 30%
c. 50%
d. None of the above

ANSWER: 50%
 

    Discussion

  • Ajay Kumar Behera   -Posted on 08 Jun 24
    300000*200/300=200000
    Contribution=3L-2L=100000
    BEP=50k/1L*100=50