Numerical - Calculate semi-variable cost at 100% production

Q.  If semi-variable cost at 60% level of production is Rs 40,000 and at 80% level is Rs 44,000. What will it be at 100% level of production?
- Published on 11 Sep 15

a. Rs 40,000
b. Rs 42,000
c. Rs 44,000
d. Rs 48,000

ANSWER: Rs 48,000
 