Risk - Definition - Basic concepts of Software Testing

Q.  The problem that threatens the success of a project but which has not yet happened is called as __________.
- Published on 16 Aug 15

a. Bug
b. Error
c. Risk
d. Defect

ANSWER: Risk
 

    Discussion

  • Prajakta Pandit   -Posted on 17 Nov 15

    - The problem that threatens the success of a project but which has not yet happened is called as risk.

    - Risk is the potential of losing something of value.

    - It is a consequence of action taken in spite of uncertainty.