Q. 5/8th of a job is completed in 10 days. If a person works at the same pace, how many days will he take to complete the job?- Published on 19 Oct 15a. 4
b. 5
c. 6
d. 7
ANSWER: 6
Solution: It is given that 5/8th of the work is completed in 10 days.
=> Remaining work = 3/8th of total
Applying unitary method:
Total work will be completed in 10 * 8 / 5 days
=> It takes 16 days to complete total work