Time and Work - Quantitative Aptitude (MCQ) questions for Q. 28526
Q. When P alone does a work, he takes 25 days more than the time taken by P and Q working together to complete the work. But Q alone takes 9 days more than the time taken by P and Q working together to complete the work. In what time, P and Q together finish this work?- Published on 15 Mar 17a. 18 days
b. 20 days
c. 25 days
d. 15 days
ANSWER: 15 days