Time and Work - Quantitative Aptitude (MCQ) questions for Q. 29284
Q. Mahesh asked 32 men to build his house in 20 days. 80% of the work got completed in just 12 days. So Mahesh removed some workers. Now how many persons does he need to complete the remaining work in decided time?- Published on 11 Apr 17a. 12
b. 20
c. 32
d. 16
ANSWER: 12