Q. Choose the correct option according to given below statement.
Statement 1: Umbrella activities are independent of any one framework activity and occur throughout the process.
Statement 2: software quality assurance, software configuration management are umbrella activity.
Statement 3: software quality assurance, software configuration management are not umbrella activity.
- Published on 19 Oct 15a. Only statement 1 is correct.
b. Statement 1 and statement 2 are correct.
c. Only statement 3 is correct.
d. Statement 1 and statement 3 are correct.
ANSWER: Statement 1 and statement 2 are correct.