1) When we say ABC organization is CMMI Level 5 company, How do you describe its stage? - Published on 14 Aug 15
a. Defined
b. Managed
c. Optimized
d. Quantitatively managed
Answer
Explanation
|
ANSWER: Optimized
Explanation: No explanation is available for this question!
|
|
2) CMMI is a successor of CMM. - Published on 13 Aug 15
a. True
b. False
Answer
Explanation
|
ANSWER: True
Explanation: No explanation is available for this question!
|
|
3) Which of the following is not the objective of CMMI? - Published on 13 Aug 15
a. Produce quality product or services by process improvement
b. Increase customer satisfaction
c. Expanding market presence
d. Achieve excellence and create value for stakeholders
e. Removing the bugs in product thereby direct product improvement
Answer
Explanation
|
ANSWER: Removing the bugs in product thereby direct product improvement
Explanation: No explanation is available for this question!
|
|
4) Which of the following is not a phase of CMMI? - Published on 30 Jul 15
a. Initial
b. Quantitatively managed
c. Integrated
d. Defined
Answer
Explanation
|
ANSWER: Integrated
Explanation: No explanation is available for this question!
|
|
5) Abbreviate the term CMMI. - Published on 30 Jul 15
a. Capability Maturity Modification integration
b. Capability Managed Maturity Integration
c. Capability Maturity Model Integrator
d. Capability Maturity Model Integration
Answer
Explanation
|
ANSWER: Capability Maturity Model Integration
Explanation: No explanation is available for this question!
|
|
6) Which of the following is the Process Improvement Model? - Published on 29 Jul 15
a. CMMI
b. Agile
c. Prototyping
d. V model
Answer
Explanation
|
ANSWER: CMMI