Which one of the following is NOT a stakeholder in a project?

Options
- Project manager
- Client contact
- Both a and b
- None of the above


CORRECT ANSWER : None of the above

Discussion Board
Explanation-

Two types of project stakeholders:
-Internal stakeholders are internal to the organization.
A sponsor, An internal customer or client (if the project arose due to an internal need of an organization), A project team, A program manager, A portfolio manager
Management, Another group’s manager internal to the organization (e.g. functional manager, operational manager, admin manager, etc.).

-External Stakeholders: These stakeholders are external to the organization.
An external customer or client, An end user of project’s outcome, A supplier, Subcontractors, The government, Local communities, The media