When to stop testing?

Options
- When you run out of time
- All test cases are done
- When quality goals established in the beginning of the project are met
- When all bugs are fixed


CORRECT ANSWER : When quality goals established in the beginning of the project are met

Discussion Board
Software testing

Answer: When quality goals established in the beginning of the project are met
Solution: The testing is never ending process but as per some conditions we stop the testing process that is known as exit criteria in the test plan. Conditions like Achieve the quality goals, Project cost, Testing deadliness and management decision.
Therefore, only option C is satisfied the answer.