Which of the following techniques give the best project estimate?

Options
- Bottom up estimating
- Parametric estimating
- Analogous estimating
- Three point estimating


CORRECT ANSWER : Bottom up estimating

Discussion Board
Explanation-

Bottom-up method uses a detailed work breakdown structure, and is best for projects estimates.