Which of the following is true if your project is terminated before it is complete?

Options
- You must stop all work and release the team immediately
- You must work with the team to document the lessons learned
- You must keep the team working on the project to give your senior management time to talk
- to the client
- You must update the project management plan to reflect this change


CORRECT ANSWER : You must work with the team to document the lessons learned

Discussion Board
Explanation-

When closing the project, the project manager will review all prior information from the previous phase closures to ensure that all project work is complete and that the project has met its objectives. Since project scope is measured against the project plan, the project manager will review that document to ensure completion before considering the project closed. Lessons learned process is established the procedures to investigate and document the reasons for actions taken if a project is terminated before completion.


Sapna Ambadkar 03-17-2017 07:42 AM

Write your comments


Enter the code shown above:

(Note: If you cannot read the numbers in the above image, reload the page to generate a new one.)


Advertisement