To which phase will training cost fall?
Options
- Failure
- Prevention
- Build
- Appraisal
CORRECT ANSWER : Prevention
Discussion Board
Training cost
Answer: Prevention
Solution: Preventive: It includes those activities that are used to reduce the defects like: statistical process, training etc.
Appraisal: It includes those activities that are used to identify the defects before the product go live.
Failure: If any product or software is failing to satisfy the requirement.
Therefore, Prevention is correct answer.
Rohit Srivastava 07-22-2014 06:52 AM
« Previous
Next »
Write your comments
*
*
Email must be in the form someone@domain.com
*
*
Enter the code shown above:
Please enter the code shown above
(Note: If you cannot read the numbers in the above image, reload the page to generate a new one.)
Related Content
Testing (25)
Testing (25)
Testing skills - Freshers (20)
Testing skills - Experienced (20)
Load Runner (30)
Manual testing (70)
QC (30)
QTP (30)
Selenium (30)
Winrunner (30)
SDLC (30)
Advertisement
▲