A does a work in 8 days and B does the same work in 16 days. In how many days they together will do the same work?
Options
- 5.33 days
- 5.50 days
- 5.75 days
- None
CORRECT ANSWER : 5.33 days
Discussion Board
Solution
A+B=A*B/A+B
=8*16|8+16
=128/24
=5.33days
Janaki 04-10-2019 12:43 PM