If 18 pumps can raise 2170 tonnes of water in 10 days, working 7 hours a day; in how many days will 16 pump raise 1736 tonnes of water, working 9 hours a day?
Options
- 6
- 7
- 8
- 9
CORRECT ANSWER : 7