In which model functional expertise can be used to estimate cost?
Options
- Function point
- Expert judgment
- Top-down
- Bottom-up
CORRECT ANSWER : Expert judgment
Discussion Board
Estimate cost
Answer: Expert judgment
Solution: Function Point: It is used to measure the size of the application or system.
Expert Judgment: It is a cost estimator that is used to make a judgment or assumption about the cost of the develop product.
Top-down & Bottom-up: These are the integration techniques that are used to integrate all unit modules into a single system.
Therefore, expert judgment is the correct answer.
Rohit Srivastava 07-23-2014 01:40 AM
« Previous
Next »
Write your comments
*
*
Email must be in the form someone@domain.com
*
*
Enter the code shown above:
Please enter the code shown above
(Note: If you cannot read the numbers in the above image, reload the page to generate a new one.)
Related Content
Testing (25)
Testing (25)
Testing skills - Freshers (20)
Testing skills - Experienced (20)
Load Runner (30)
Manual testing (70)
QC (30)
QTP (30)
Selenium (30)
Winrunner (30)
SDLC (30)
Advertisement
▲