Triple constraint consists of _______
Options
- Cost, schedule, and quality
- Cost, resources, and schedule
- Cost, schedule, and scope
- Cost, schedule, and product
CORRECT ANSWER : Cost, schedule, and scope
Discussion Board
Explanation-
The triple constraint is the combination of the three most significant restrictions on any project: scope, schedule and cost
Sapna Ambadkar 03-17-2017 08:36 AM
« Previous
Next »
Write your comments
*
*
Email must be in the form someone@domain.com
*
*
Enter the code shown above:
Please enter the code shown above
(Note: If you cannot read the numbers in the above image, reload the page to generate a new one.)
Related Content
PMP (25)
PMP (25)
SoftwareEngineering (25)
Software Engineering (47)
Software Engineering (50)
Advertisement
▲