Shashank and Prateek together can complete a piece of work in 8 days. If Shashank alone can complete the same work in 24 days, in how many days can Prateek alone complete the same work?

Options
- 12 days
- 14 days
- 16 days
- 18 days


CORRECT ANSWER : 12 days

Discussion Board
Answer

s+p=1/8
s=1/24
p=?
p=1/8-1/24=1/12
by inverting 12 days