Which of the following is not an input of the Contract Administration process?

Options
- Work Performance Information
- Procurement Management Plan
- Contract Management Plan
- Selected Sellers


CORRECT ANSWER : Procurement Management Plan

Discussion Board
Explanation-

Procurement Management Plan is not an input of the Contract Administration process.

The inputs for Contract Administration process are:

Contract- A contract is an agreement between the buyer and the seller which details their legal requirements and obligations.

Contract Management Plan - The Contract Management Plan utilizes the existing contract requirements to provide the buyer and the seller with guidelines for administering and monitoring contracts for significant purchases or acquisitions.

Selected Sellers - The selected sellers are sellers that the buyer deems the best candidates for the project and that have negotiated a draft contract.

Performance Reports - Performance reports are more detailed than work performance information, they use methods such as bar charts and S-curves to organize and summarize information such as earned value management and project work progress.

Approved Change Requests - Approved change requests verify which changes to contracts or procurement procedures have been processed and approved.

Work Performance Information - Work performance information comes from the Direct and Manage Project Execution process, provides statuses of the project schedule activities being done to accomplish the project work. The team uses it to monitor the sellers progress on schedule, deliverables, and costs.