Solid Blue line indicated that

Options
- Test to be executed after the previous test, with no condition.
- Test to be executed only if the previous test has finished.
- Test to be executed only if the previous test has status passed.
- All of these.


CORRECT ANSWER : Test to be executed only if the previous test has finished.

Discussion Board
Quality Center

Answer: Test to be executed only if the previous test has finished.
Solution: In the QC, there are 2 different blue lines that are used for indication, one is dashed blue and other one is solid blue. Solid Blue line indicates the test to be executed only if the previous test result has ‘Finished’ and Dashed Blue line indicates which test is to be executing after the previous test.
Therefore, option B is the correct answer.