You are managing a project where you work with 7 other team members and two sponsors. How many lines of communications are there between stakeholders on this project?
Options
- 21
- 36
- 45
- 54
CORRECT ANSWER : 45
Discussion Board
45
Formula to calculate lines of communication is: n*(n-1)/2.
Here, the statement given is: you work with 7 other team members i.e 7(team members)+1(you)+2 sponsors=10. Hence, N=10.
10*(10-1)/2=45.
Therefore, the lines of communications between stakeholders on this project is: 45
Sapna Ambadkar 03-20-2017 02:55 AM
« Previous
Next »
Write your comments
*
*
Email must be in the form someone@domain.com
*
*
Enter the code shown above:
Please enter the code shown above
(Note: If you cannot read the numbers in the above image, reload the page to generate a new one.)
Related Content
PMP (25)
PMP (25)
SoftwareEngineering (25)
Software Engineering (47)
Software Engineering (50)
Advertisement
▲