« Previous
A risk register does not contain
Options
- List of identified risks
- List of methods used to identify risks
- Root causes of risks
- Updated risk categories
CORRECT ANSWER : List of methods used to identify risks
Discussion Board
Explanation-
Risk register contains the list of all identified risks, their root causes, category, responses and update risk categories.