A can do a certain job in 8 days. B is 50% more efficient than A. how many days does B alone take to do the same job?
Options
- 3 days
- 4 days
- 5 days
- None
CORRECT ANSWER : None
Discussion Board
Solution
A can do a work in 8 days means A do 1/8wrk a day. Also given B is 50%more efficient than A.
ie, A=100% and B=150%
ie, 1/B=1/8*(150/100)
=1/8*(3/2)
=3/16
ie, B =16/3
Dichu 10-24-2019 03:10 AM
hi
answer is 16/3
manasa 10-3-2019 03:47 AM
explation
please the explation solution in step wise this type of problems i feel problematic please explain solution as early as possible
satya 09-5-2019 08:06 AM
« Previous
Write your comments
*
*
Email must be in the form someone@domain.com
*
*
Enter the code shown above:
Please enter the code shown above
(Note: If you cannot read the numbers in the above image, reload the page to generate a new one.)
Advertisement
▲