What is decomposition?
Options
- Waiting for a task to expire so that it can break down into smaller tasks
- Taking a deliverable and breaking it down into the smaller work packages so that it can be organized and planned
- Categorizing work packages
- Dividing work packages into deliverables that can be planned for.
CORRECT ANSWER : Taking a deliverable and breaking it down into the smaller work packages so that it can be organized and planned
Discussion Board
Explanation-
Answer is, Taking a deliverable and breaking it down into the smaller work packages so that it can be organized and planned. Because, decomposition is a technique used for dividing and subdividing the project scope and project deliverables into smaller and more manageable parts.
Sapna Ambadkar 03-17-2017 05:12 AM
« Previous
Next »
Write your comments
*
*
Email must be in the form someone@domain.com
*
*
Enter the code shown above:
Please enter the code shown above
(Note: If you cannot read the numbers in the above image, reload the page to generate a new one.)
Related Content
PMP (25)
PMP (25)
SoftwareEngineering (25)
Software Engineering (47)
Software Engineering (50)
Advertisement
▲