In quantifying risk, the term RE represents
Options
- Risk expense
- Related expense
- Risk exposure
- Risk evaluation
CORRECT ANSWER : Risk exposure
Discussion Board
Software Testing
Answer: Risk exposure
Solution: Quantifying Risk: The quantifying risk is used to concrete or analyze the impact of the risk. The RE represents the risk exposure and it is also called risk impact. RE is defined by the probability of the risk and the loss.
Therefore, Risk Exposure is a correct answer.
Rohit Srivastava 07-28-2014 06:17 AM
« Previous
Next »
Write your comments
*
*
Email must be in the form someone@domain.com
*
*
Enter the code shown above:
Please enter the code shown above
(Note: If you cannot read the numbers in the above image, reload the page to generate a new one.)
Related Content
Testing (25)
Testing (25)
Testing skills - Freshers (20)
Testing skills - Experienced (20)
Load Runner (30)
Manual testing (70)
QC (30)
QTP (30)
Selenium (30)
Winrunner (30)
SDLC (30)
Advertisement
▲