As a project manager you are preparing a high level WBS. Which process group you are in?

Options
- Planning
- Executing
- Controlling
- Initiating


CORRECT ANSWER : Initiating

Discussion Board
Explanation-

High-level constraints are identified in the project charter, which is created during project initiating.