As a project manager you are preparing a high level WBS. Which process group you are in?
Options
- Planning
- Executing
- Controlling
- Initiating
CORRECT ANSWER : Initiating
Discussion Board
Explanation-
High-level constraints are identified in the project charter, which is created during project initiating.