Project indicators enable a software project manager to ___________________

Options
- Assess the status of an ongoing project
- Track potential risks
- Uncover problem area before they “go critical”
- All of above


CORRECT ANSWER : All of above

Discussion Board
Explanation-

Process Indicators:

-Metrics should be collected so that process and product indicators can be ascertained.
-Process indicators enable software project managers to: assess project status, track potential risks, detect problem area early, adjust workflow or tasks, and evaluate team ability to control product quality.