A can do a piece of work in 60 days. He works at it for 10 days and then B alone finishes the remaining work in 40 days. In how much time will A and B , working together, finish the work?
Options
- 25 days
- 30 days
- 35 days
- None
CORRECT ANSWER : 25 days