1. Project A involves building factories at prospective locations and project B involves expanding factories at present location by acquiring nearby plots. Benefit yields for project A and project B are Rs.25,00,00,000 and Rs.18,00,00,000 respectively. Project A has been chosen because of its greater benefit yield. What is the opportunity cost of doing Project A?
|
|
|
|