Time and Work - Aptitude test, questions, shortcuts, solved example videos

Video on Time and Work - shortcuts, tips and tricks

Time & Work

Work is always considered as an entire value or one. There exists an analogy between the time-speed-distance problems and work. Work based problems are more or less related to time speed and distance.

Important Formulae:

1) Work from days:
If a person can do a work in 'n' days, then person's 1 day work = 1 / n

2) Days from work:
If a person's 1 day work is equal to 1/n , then the person can finish the work in 'n' days.
3) Numer of Days = Total Work
Work Done in 1 Day

Quick Tricks & Tips:

1) Ratio:

If 'A' is 'x' times as good a workman as 'B', then
a) Ratio of work done by A & B in equal time = x: 1
b) Ratio of time taken by A & B to complete the work = 1: x. This means that 'A' takes (1/xth) time as that of 'B' to finish same amount of work.

For example,
if A is twice good a workman as B, then it means that

a) A does twice as much work as done by B in equal time i.e. A:B = 2:1
b) A finishes his work in half the time as B

2) Combined Work:

a) If 'A' and 'B' can finish the work in 'x' & 'y' days respectively, then
A's one day work = 1
x

B's one day work = 1
y

(A + B)'s one day work = 1 + 1 = (x + y)
xyxy
Together, they finish the work in xy days.
(x + y)

b) If 'A', 'B' & 'C' can complete the work in x, y & z days respectively, then
(A + B+ C) 's 1 day work = 1 + 1 + 1 = (xy + yz + xz)
xyzxyz
Together, they complete the work in xyz days.
xy + yz + xz

c) If A can do a work in 'x' days and if the same amount of work is done by A & B together in 'y' days, then
A's one day work = 1
x
(A+B)'s one day work = 1
y
B's one day work = 11 = x – y
yxxy
So, 'B' alone will take xydays.
x – y

d) If A & B together perform some part of work in 'x' days, B & C together perform it in 'y' days and C & A together perform it in 'z' days, then
(A + B)'s one day work = 1
x
(B + C)'s one day work = 1
y
(C + A)'s one day work = 1
z
1 + 1 + 1 = 2(A+B+C)'s 1 one day work
xyz
Now, we have at hand (A + B + C)'s one day work =
1 + 1 + 1
xyz
2
 
(A+ B+ C) will together complete the work in  days
2
1 + 1 + 1
xyz

If A works alone, then deduct A's work from the total work of B & C to find the time taken by A alone.

For A working alone, time required =A's work - (A+B+C)'s combined work
=  
2
11 + 1
xyz
= 2xyz days
[xy + yz – zx]

Similarly,
- If B works alone, then time required = 2xyz
(– xy + yz + zx)
- If C works alone, then time required = 2xyz
(xy – yz + zx)

3) Man -Work -Hour related problems:
Remember that M D H = Constant
W
where,
M: Number of Men
D: Number of Days
H: Number of Hours
W: Amount of Work done

If men are fixed, work is proportional to time. If work is fixed , time is inversely proportional to men. Thus,

M1 x T1 = M2 x T2
W1W2

Once you have understood the following simple things, this chapter will become extremely easy for you.

a) Work and time are directly proportional to each other
b) Number of men and time are inversely proportional to each other
c) And, work can be divided into equal parts i.e. if a task is finished in 10 days, in one day you will finish (1/10th) part of the work.

Questions Variety:

Type 1: Efficiency of two or more workers is give separately. Find how much time would they take to finish the work together.


Examples:

Q 1. Reema can complete a piece of work in 12 days while Seema can the same work in 18 days. If they both work together, then how many days will be required to finish the work?

a. 6 days
b. 7.2 days
c. 9.5 days
d. 12 days
View solution

Correct answer : (b)

Hint:

A's one day work = 1
12
B's one day work = 1
18
(A + B)'s one day work = 1 + 1 = (18 + 12) = 30 = 1
1218(12 x 18)2167.2
Together, A & B will finish the work in 7.2 days.


Q 2. If 'A' completes a piece of work in 3 days, which 'B' completes it in 5 days and 'C' takes 10 days to complete the same work. How long will they take to complete the work , if they work together?
a. 1.5 days
b. 4.5 days
c. 7 days
d. 9.8 days
View solution

Correct answer :(a)

Hint:

A's one day work = 1
3
B's one day work = 1
5
C's one day work = 1
10
(A+ B+ C)'s one day work = 1 + 1 + 1 = 1
35101.5
Hence, A ,B & C together will take 1.5 days to complete the work.

Type 2: Find the time required to complete the work
a) by one worker if the total time taken by all workers and one of the workers are given.
b) either alone or together by the workers for the given times of workers in combined form.


Examples:

Q 3. Two painters 'P1' & 'P2' paint the bungalow in 3 days. If P1 alone can paint the bungalow in 12 days, in how many days can 'P2'' alone complete the same paint work?

a. 4 days
b. 6 days
c. 9 days
d. 12 days
View solution

Correct answer: (a)

Hint:

If a person can do a part of work in 'n' days, then person's work in 1 day = 1
n
As painters P1 & P2 paint the bungalows in 3 days, then work done by both painters = 1
3
As P1 paint it alone in 12 days, then work done by painter P1 = 1
12
Work done by painter P2 = 11 = 4 – 1 = 3 = 1
31212124
Therefore, same work will be completed by painter P2 in 4 days.


Q 4. A & B can make paintings in 6 days, B & C can can make those paintings in 10 days. If A, B & C together can finish the work in 4 days, then A & C together will do it in ________ days.

a. 4 (2/7) days
b. 1/ 8 days
c. 2 (2/5) days
d. 6 (3/ 8) days
View solution

Correct answer: (a)

Hint:
We are given that, A,B, & C together complete the work in 4 days.

We can write, (A+B+C) 's 1 day work = 1
4
Similarly, (A+B) 's 1 day work = 1/6 days & (B+C)'s 1 day work = 1
10

Since the work is divided in combination and we are asked to find out the combined work of (A + C), so we can find out,
(A + C)'s 1 day work = [2 (A+B+C)'s 1 day work] – [(A+ B) 's 1 day work + (B+C)'s 1 day work]
= 2 x 11 + 1
4610
= 116 = 14 = 7
26021530
Hence, A & C together can complete the work in 30 /7 days = 42days.
7

Type 3: Find the time required
a) to complete the work together if one worker is 'm' times as efficient as the other worker & takes 'D' days less than the other worker
b) to complete the work by one of the workers if they work together or if work efficiencies of two workers are given.


Examples:

Q 5. Pooja is twice as efficient as Aarti and takes 90 days less than Aarti to complete the job. Find the time in which they can finish the job together.

a. 30 days
b. 45 days
c. 60 days
d. 90 days
View solution

Correct answer :(c)

Hint:
Assume that Pooja completes the job in 'x' days.
So, Aarti will take '2x' days to complete the same job.

As Pooja takes 90 days less than Aarti, we get
x = 2x – 90
By solving this equation, we get x = 90 .
Thus, 2x = 2 x 90 = 180

Part of job done by Pooja in 1 day = 1/ 90
Part of job done by Aarti in 1 day = 1/180

(Part of job done together in 1 day) = (Part of job done by Pooja in 1 day) + (Part of job done by Aarti in 1 day)
= (1/90) + (1/180)
= 3/180
=1/60
(1/60)th part of whole job will be completed by Pooja and Aarti together in one day.

Therefore, the whole job will be completed in 60 days together.

Alternate Method: Since 'A' is 'm' times as efficient as 'B' & takes 'D' days less than 'B', then the time required to complete the job together is given by,

T = m x D
(m2 – 1)
T = 2 x 90 / [(2)2 - 1] = 180 / 3 = 60 days


Q 6. Monika is twice as good as Sonika and together they complete a piece of work in 20 days. In how many days will Monika alone will finish the work?

a. 22 days
b. 30 days
c. 37 days
d. 52 days
View solution

Correct answer : (b)

Hint: If 'A' is 'x' times as good a workman as 'B', then ratio of work done by A & B = x: 1
Monika's 1 day work : Sonika's 1 day work = 2:1
(Monika's + Sonika's ) 1 day work = 1 /20

Divide 1/20 in the ratio 2:1 ---------( To divide the number 'a' into ratio x & y , we have first part = ax / x + y )

Therefore, Monika's 1 day work = 1 x 2 + 1 = 1
20230

Hence, Monika will alone finish the work in 30 days.

Type 4: Calculate the time required by men or (combination of men with other people) to complete a certain work in certain hours for the given another set of number of required men, work & hours.


Examples:

Q 7. 6 men can pack 12 boxes in 7 days by working for 7 hours a day. In how many days can 14 men pack 18 boxes if they work for 9 hours a day?
a. 3.5 days
b. 5 days
c. 7.5 days
d. 12 days
View solution

Correct answer :(a)

Hint: If 'w1' work is done by 'm1' men by working for 'h1' hours per day in 'd1' days & 'w2' is work done by men 'm2' working for 'h2' hours per day in 'd2' days, then

m1d1h1 = m2d2h2
w1w2
Since we need to find 'd2', we can re-arrange the formula as,
d2 = m1d1h1w1
m12h2w1
= 6 x 7 x 7 x 18
14 x 9 x 12
= 3.5 days


Q 8. 4 men and 5 boys can do a piece of work in 20 days while 5 men and 4 boys can do the same work in 16 days. In how many days can 4 men and 3 boys do the same work?

a. 10 days
b. 15 days
c. 20 days
d. 25 days
View solution

Correct answer:(c)

Hint:
Assume 1 man's 1 day work = x & 1 boy's 1 day work = y
From the given data, we can generate the equations as : 4x + 5y = 1/20 ---(1) & 5x + 4y = 1/16 ---(2)
By solving the simultaneous equations (1) & (2),
x = 1/ 80 & y = 0

Therefore, (4 men + 3 boys ) 1 day work = 4 x 1 + 3 x 0 = 1
8020
Thus, 4 men and 3 boys can finish the work in 20 days.


Practice questions on Time and Work
Simple Interest - Aptitude test, questions, shortcuts, solved example videos
Simple Interest - Quantitative aptitude tutorial with easy tricks, tips, short cuts explaining the concepts. Online aptitude preparation material with practice question bank, examples, solutions and explanations. Video lectures to prepare quantitative aptitude for placement tests and competitive exams like MBA, Bank exams, RBI, IBPS, SSC, SBI, RRB, Railway, LIC, MAT. Very useful for freshers, engineers, software developers taking entrance exams. Learn and take practice tests!
Problems on Percentage - Aptitude test, questions, shortcuts, solved example videos
Problems on Percentage - Quantitative aptitude tutorial with easy tricks, tips, short cuts explaining the concepts. Online aptitude preparation material with practice question bank, examples, solutions and explanations. Video lectures to prepare quantitative aptitude for placement tests and competitive exams like MBA, Bank exams, RBI, IBPS, SSC, SBI, RRB, Railway, LIC, MAT. Very useful for freshers, engineers, software developers taking entrance exams. Learn and take practice tests!
Profit and Loss - Aptitude test, questions, shortcuts, solved example videos
Profit and Loss - Quantitative aptitude tutorial with easy tricks, tips, short cuts explaining the concepts. Online aptitude preparation material with practice question bank, examples, solutions and explanations. Video lectures to prepare quantitative aptitude for placement tests and competitive exams like MBA, Bank exams, RBI, IBPS, SSC, SBI, RRB, Railway, LIC, MAT. Very useful for freshers, engineers, software developers taking entrance exams. Learn and take practice tests!
Post your comment
Discussion Board
Time and work
A can do a piece of work in 20 days and B in 30 days. They work together for 7 days and then both leave the work then C alone finishes the remaining work in 10 days in how many days will C finish the whole work
Harshal Gorghate 10-6-2021
Tspsc
Very nice n clear explanation. Thank you. Now understood the topic n got confidence too.
Srujana 04-1-2019
time and work
pipe 1 can fill a tank in 12 hours, pipe 2 in 20 hours while a leak can empty the tank in 30 hours. Initially, all 3 are opened. After 5 hours, pipe 1 is closed. In how much more time will the tank get completely filled
mahima 01-30-2019
wrong solution
QUESTION 8 OF TIME AND WORK

on solving the equations the value of man is coming out to be 0 and the value of boys is coming to be 4.
so for 4 men and 3 boys
3*4=12 days should be the answer
pranjali pandey 08-9-2018
about time and work problem
X=1/5,Y=1/9,Z=1/15
together they can work as X+Y+Z=17/45
i.e time taken to complete work by all the three together=45/17=2.64 hrs
but given X leaves after 1 hr so work left after 1 hour =2.64-1=1.64
It is given remaining work is done by Y and Z
=Y+Z=8/45
By LHS=RHS
left over work which can done by X,Y,Z= Work done by Y and Z
1.64(17/45)=k(8/45)
where as k is the time taken by Y and Z together.
On simplification we get K=3.48
so 3.48 hrs is required by Y and Z to complete the remaining work
Akhil 05-28-2018
Time n work
X can do a piece of work in 5 hours, Y in 9 hours and Z in 15 hours. if Z could work with them for 1 hour only, the time taken by X and Y together to complete the work is.
Plz tell me how to solve this !
Anonymous 10-19-2017
Aptitudeonline test answers with explanation
Aptitudeonline test answers with explanation
sravanthi 07-16-2014
answers
put answers along with aptitude questions
srinivas 06-16-2013