Demand Factor - MCQs with answers

Demand Factor - MCQs with answers


Q1. What is the result of the product of diversity factor and maximum demand?

a. Average demand
b. Sum of consumers maximum demand
c. Installed capacity.
d. Generated power.

View Answer / Hide Answer

ANSWER: b. Sum of consumers maximum demand



Q2. Maximum demand on the power system is

a. Sum of the maximum demands of all its consumers.
b. Greatest average load in a specified time.
c. Peak value of load in a specified time.
d. All of the above.

View Answer / Hide Answer

ANSWER: b. Greatest average load in a specified time.



Q3. What is demand factor?

a. Average load to maximum demand.
b. Maximum demand to connected load.
c. Connected load to maximum demand.
d. Maximum demand to average load.

View Answer / Hide Answer

ANSWER: b. Maximum demand to connected load.



Q4. What is the value of demand factor?

a. Greater than unity.
b. Less than unity.
c. Always more than unity.
d. Normally more than unity.

View Answer / Hide Answer

ANSWER: b. Less than unity.



Q5. What is connected load?

a. Installed electrical load in the premises of the consumer.
b. Maximum load a consumer draws.
c. Load drawn by a consumer at any instant.
d. None of the above.

View Answer / Hide Answer

ANSWER: a. Installed electrical load in the premises of the consumer.



Q6. The power system experiences peak demand from

a. Midnight to 8 A.M
b. 8 A.M to 2 P.M
c. 2 P.M to 6 P.M
d. 6 P.M to 10 P.M

View Answer / Hide Answer

ANSWER: d. 6 P.M to 10 P.M



Q7. The maximum demand on the power system is 100 MW. If the annual load factor is 40%. Calculate the total energy generated in a year.

a. 3761 * 105 kWh
b. 4174 * 105 kWh
c. 3504 * 105 kWh
d. 3500 * 105 kWh

View Answer / Hide Answer

ANSWER: c. 3504 * 105 kWh



Q8. The power demand can be estimated approximately by

a. Load survey method.
b. Mathematical method.
c. Statistical method.
d. Economic parameters.

View Answer / Hide Answer

ANSWER: c. Statistical method.



Q9. A generating station has a connected load of 55 MW and maximum demand of 20 MW. What is the demand factor?

a. 0.4785
b. 0.3636
c. 2.75
d. 1100

View Answer / Hide Answer

ANSWER: b. 0.3636



Q10. Determine the average demand of a plant if its load factor and maximum demand are 0.60 and 30 MW.

a. 20 MW
b. 18 MW
c. 50 MW
d. 13 MW

View Answer / Hide Answer

ANSWER: b. 18 MW