Time and Work - Quantitative Aptitude (MCQ) questions for Q. 28524
Q. A can do a work in 3 days. B can do the same work in 6 days and C can do the same work in 7 days. If they work together, in how many days will they take to complete the work?- Published on 15 Mar 17a. 11/10 Days
b. 15/16 Days
c. 14/9 Days
d. 16/7 Days
ANSWER: 14/9 Days