Q.  P can do a job in 30 days, while Q alone can do it in 45 days. They work together for 15 days and rest of the job is done by R in 6 days. They get Rs.15000 for the whole job. What will be R’s share?
- Published on 10 Mar 17

a. Rs. 5000
b. Rs. 2500
c. Rs. 7500
d. Rs. 1500

ANSWER: Rs. 2500
 