1) Every risk has 100% likelihood. - Published on 18 Aug 15
a. True
b. False
Answer
Explanation
|
ANSWER: False
Explanation: No explanation is available for this question!
|
|
2) What is associated with the Product Risk? - Published on 14 Aug 15
a. Control of test item
b. Negative consequences
c. non-availability of test environment
d. Test object
Answer
Explanation
|
ANSWER: Test object
Explanation: No explanation is available for this question!
|
|
3) Which is / are the ways to deal with a Risk? - Published on 14 Aug 15
a. Mitigate
b. Contingency
c. Transfer
d. Ignore
e. All of the above
Answer
Explanation
|
ANSWER: All of the above
Explanation: No explanation is available for this question!
|
|
4) Choose the correct option according to the given statements regarding Risk Management.
Statement 1: A risk is a potential problem - it might happen, it might not. Statement 2: Managers, software engineers, and customers participate in Risk Analysis and Management. Statement 3: Only Managers participate in Risk Analysis and Management. - Published on 14 Aug 15
a. Statement 1 and 2 are correct
b. Only statement 1 is correct
c. Only statement 3 is correct
d. Statement 1 and 3 are correct
Answer
Explanation
|
ANSWER: Statement 1 and 2 are correct
Explanation: No explanation is available for this question!
|
|
5) What is Risk? - Published on 14 Aug 15
a. Negative consequence that could occur
b. Negative consequence that will occur
c. Negative consequence that must occur
d. Negative consequence that shall occur
Answer
Explanation
|
ANSWER: Negative consequence that could occur
Explanation: No explanation is available for this question!
|
|
6) Risk is expressed in terms of probability and impact. - Published on 14 Aug 15
a. True
b. False
Answer
Explanation
|
ANSWER: True
Explanation: No explanation is available for this question!
|
|
7) Risk Management is a responsibility of the _________. - Published on 14 Aug 15
a. Customer
b. Investor
c. Developer
d. Project team
e. Production team
Answer
Explanation
|
ANSWER: Project team
Explanation: No explanation is available for this question!
|
|
8) As a tester which of the following will come under product risk if you are testing an e-commerce website? - Published on 14 Aug 15
a. Shortage of testers
b. Many changes in SRS that caused changes in test cases
c. Delay in fixing defects by development team
d. Failure to transfer a user to secure gateway while paying
e. All of the above
Answer
Explanation
|
ANSWER: Failure to transfer a user to secure gateway while paying
Explanation: No explanation is available for this question!
|
|
9) Risk Management is important part of a Project Management. - Published on 14 Aug 15
a. True
b. False
Answer
Explanation
|
ANSWER: True
Explanation: No explanation is available for this question!
|
|
10) Software risk always involves two characteristics. What are those characteristics? - Published on 13 Aug 15
a. Uncertainty and Loss
b. Certainty and Profit
c. Staff size and Budget
d. Project Deadline and Budget
Answer
Explanation
|
ANSWER: Uncertainty and Loss