Which of the following shows roles and responsibilities of a project?
Options
- Bar chart
- Resource histogram
- RACI matrix
- Human Resource Management Plan
CORRECT ANSWER : RACI matrix
Discussion Board
Explanation-
RACI shoes the responsibility of project. RACI, map out who is Responsible, is Accountable, must be Consulted with, and shall stay Informed.
-Responsible – Who is completing the task.
-Accountable – Who is making decisions and taking actions on the task(s).
-Consulted – Who will be communicated with regarding decisions and tasks.
-Informed – Who will be updated on decisions and actions during the project.
Sapna Ambadkar 03-17-2017 03:09 AM
Next »
Write your comments
*
*
Email must be in the form someone@domain.com
*
*
Enter the code shown above:
Please enter the code shown above
(Note: If you cannot read the numbers in the above image, reload the page to generate a new one.)
Related Content
PMP (25)
PMP (25)
SoftwareEngineering (25)
Software Engineering (47)
Software Engineering (50)
Advertisement
▲