Which of the following shows roles and responsibilities of a project?

Options
- Bar chart
- Resource histogram
- RACI matrix
- Human Resource Management Plan


CORRECT ANSWER : RACI matrix

Discussion Board
Explanation-

RACI shoes the responsibility of project. RACI, map out who is Responsible, is Accountable, must be Consulted with, and shall stay Informed.
-Responsible – Who is completing the task.
-Accountable – Who is making decisions and taking actions on the task(s).
-Consulted – Who will be communicated with regarding decisions and tasks.
-Informed – Who will be updated on decisions and actions during the project.