When is stakeholder analysis performed?

Options
- When defining the project scope
- When developing the project charter
- When creating the project management plan
- Whenever changes happen through change control


CORRECT ANSWER : When defining the project scope

Discussion Board
Explanation-

Stakeholder analysis as part of the scope definition process that produced the project scope statements as an output.