____________ shows the accumulation of defects in QC project.

Options
- Defect Summary Graph
- Defect Progress Graph
- Defect Age Graph
- Defect Trend Graph.


CORRECT ANSWER : Defect Progress Graph

Discussion Board
Quality Center

Answer: Defect progress graph
Solution: Defect Summary Graph: Defect summary graph is used to represent the summary of number of defects in project and also defines the estimate time for fixing defects.
Defect Progress Graph: Defect progress graph is used to represent the accumulation of defects in QC project.
Defect Age Graph: Defect Age graph is used to present the life status history of defects in a projects.
Defect Trend Graph: Defect Trend graph is used to represent the history of changes perform in the QC project for each time interval.
Therefore, Defect Progress Graph is the correct answer.