________ shows the history of changes to specific requirement field on QC Project.

Options
- Requirement Progress Graph.
- Requirement Coverage Graph.
- Requirement Trend Graph.
- Both B and C.


CORRECT ANSWER : Requirement Trend Graph.

Discussion Board
Quality Center

Answer: Requirement Trend Graph
Solution: Requirement Progress Graph: This type of graph is used to display Specified requirement or information for a period of type. The progress graph is used in each phase of testing.
Requirement coverage Graph: This Graph is used to display the coverage of the requirement. It displays which test is linked with specified Requirement.
Requirement Trend Graph: The Requirement Trend Graph is used to display the history of changes for a specified requirement.
Therefore the suitable answer is Requirement Trend Graph.