Rama can do a piece of work in 60 days. Tanu is 50% more efficient than Rama. The number of days taken by Tanu to do the same piece of work.
Options
- 30 days
- 35 days
- 40 days
- 50 days
CORRECT ANSWER : 40 days
Discussion Board
answer
ans is 40 days