Test Readiness review is conducted by the

Options
- Project manager
- Test manager
- Quality assurance personnel
- User/Customer


CORRECT ANSWER : Test manager

Discussion Board
Test readiness

Answer: Test manager
Solution: Test Readiness review (TRR) is performed to determine that the developed system is ready for the formal testing or not by the test manager.