A statistical technique to assess, monitor and maintain the stability of a process is

Options
- Pareto chart
- Control chart
- Run chart
- Histogram


CORRECT ANSWER : Control chart

Discussion Board
Control chart

Answer: Control chart.
Solution: Pareto chart: It is also known as 80-20 rule, that represents how much time required for completing the work.
Control chart: This chart is used to represent if the process is in control state or not.
Run chart: It is also known as run sequence plot that displays a graphical representation of execution.
Histogram: Histogram refers to the bar chart because it uses Bars of different size to represent the data or value.
Therefore, option B is a correct answer.