A project can have all of the below mentioned characteristics except
Options
- being temporary
- being unique
- having a definite beginning and end
- repeating every month
CORRECT ANSWER : repeating every month
Discussion Board
Explanation-
- It is temporary: temporary means that every project has a definite beginning and a definite end. Project always has a definitive time frame.
- A project creates unique deliverables, which are products, services, or results.
- A project creates a capability to perform a service.
-Project is always developed in steps and continuing by increments: Progressive Elaboration.
Sapna Ambadkar 03-16-2017 06:21 AM
« Previous
Next »
Write your comments
*
*
Email must be in the form someone@domain.com
*
*
Enter the code shown above:
Please enter the code shown above
(Note: If you cannot read the numbers in the above image, reload the page to generate a new one.)
Related Content
PMP (25)
PMP (25)
SoftwareEngineering (25)
Software Engineering (47)
Software Engineering (50)
Advertisement
▲