A project can have all of the below mentioned characteristics except

Options
- being temporary
- being unique
- having a definite beginning and end
- repeating every month


CORRECT ANSWER : repeating every month

Discussion Board
Explanation-

- It is temporary: temporary means that every project has a definite beginning and a definite end. Project always has a definitive time frame.
- A project creates unique deliverables, which are products, services, or results.
- A project creates a capability to perform a service.
-Project is always developed in steps and continuing by increments: Progressive Elaboration.