The float of activities in a critical path is

Options
- always positive
- always negative
- always zero
- cannot be determined


CORRECT ANSWER : always zero

Discussion Board
Explanation-

Zero float is a condition where there is no excess time between activities. An activity with zero float is considered a critical activity.