Which of the following best describes the main purpose of the project charter?

Options
- It authorizes the project manager to work on the project
- It identifies the sponsor and describes his or her role on the project
- It contains a list of all activities to be performed
- It describes the initial scope of the work


CORRECT ANSWER : It authorizes the project manager to work on the project

Discussion Board
Explanation-

A project charter names the project manager and defines the authority of the project manager. It gives the project manager the authority to utilize organizational resources to accomplish the project objectives.